Overall Main Floor

The school is attached to the recreation complex and students will utilize the soccer pitch and the three associated gymnasiums for educational programming. Other aspects of the recreation complex such as the skating rink will also be available for student use.  ( left click to enlarge)

335 total views, no views today

Partial Main Floor

Classrooms, associated Break Out Rooms and oversized furnished hallways are all designed to promote student mixing and collaborative learning. Classrooms and hallways are connected to the outdoors though many windows and through shared outdoor classroom spaces as well as through Green Roof spaces on top of boot rooms. There is a 400 seat theatre that the community will have access to.

349 total views, 1 views today

Partial Second Floor

The main student entry into the school takes place through the second floor of the recreation complex and along the second floor corridor of the school. This route passes by the recreation center cafeteria that students will have access to.             (left click to enlarge)                                                       Â

519 total views, 2 views today

Design June 2011(33% Completion)

                                                  Classrooms Main Floor

                                                                                                    Second Floor Classrooms and Library

Front Entry

Parent Room

Reception – Administration – Staff Room

Special Education – Therapies

 

Practical and Applied Arts                                            Theatre – Music – Gym Change Rooms

 

 

 

Classroom 1

Classroom 2

433 total views, no views today

Design/Construction Schedule

The following is an abbreviated schedule for the next few months to give you and idea where we are on the timeline for the planned school opening, September 2013.

May – August 2011:
– We have regularily scheduled engineering/construction management coordination meetings where the various parties involved in planning the school and recreation complex meet to coordinate the design and planning.

June – August 2011:
– Various construction documents including drawings are being developed for the project.

August 2011:
– 99% of the design and drawings will be complete
– End of August we expect to have final Ministry approval for the plans

September 2011:
– Tender to trades
– Ground breaking after tender review

July 2013:
– Substantial completion
– Teachers move into building

September 2013:
– Students Grade 4-8 start classess

835 total views, no views today