Timeline

  • Sept. 2006
    • feasibility Study for an integrated facility
  • June 2010
    • meeting with students
    • meeting with staff
    • meeting with the public
    • principal appointed
  • Currently working on:
    • agreement with the town to share the rec complex
    • approval from Ministry to proceed with design
  • Next Steps:
    • Design Development Report(DDR) submission
    • detailed design
    • proposed tender and construction in 2011-2013 (depending on provincial Funding)